Well things are moving at last! The granite paving around the side and rear of the Quinta is finished. The paving in the central couryard is partly done, and the paving at the front of the Quinta and behind the Adega is layed but not yet cemented. The walling around the car park and some of the paving has been completed.

In our apartment the wood burner was installed this afternoon, and I have a door to my bathroom. The 1st of December is a national holiday so nothing will happen tomorrow. We need the painters next, and then the electrician can finish, so there may be a chance we will be in our apartment for Christmas. The weather has been wet off and on for most of the month, and now has turned cold, we can see snow on the mountain tops.

Things moving at last!